Henan Daswell Machinery is a professional manufacturer of construction machine for almost 30 years in China. We are dedicated to supplying our customers with best service and products, our major products include:concrete mixer for sale,flyover construction,If you are interested in our products, please contact us freely: info@daswell.com

Concrete batching plant before commissioning checks and preparations:

1.Check the grease of the various parts of the adequacy of the good debugging must be observed mixing barrel four shaft end seal plate at grease overflow.

2.Check the various parts of the installation, connection bolts are tightened, the chain connection is reliable.

3.Check the configuration of the pneumatic system is normal discharge door is in the closed position

4.Check mixing barrel if there is a foreign body planetary concrete mixer, fastening liner Sicoma twin shaft concrete mixer, leaves again commercial concrete batching plant, mixing arm bolts to prevent shedding.

5.Check its support of the electrical system is normal.